Single-storey rear / side extension: cost a whole project, stage by stage

A ground-floor extension: design, foundations, walls, roof, openings, services, finishes. JobBosh lays the project out as 20 stages: 13 are calculated by their own recipes from your measurements; the rest - design, steel, windows, certificates - are priced from a quotation or a figure you already hold, and it says so until you have it.

The stages

StageWorkHow it is costedEnquiries it may need
Survey, design and engineeringArchitect / technologist drawings and structural engineer's calculationsDesign and engineering fees - by quotationArchitect / architectural technologist, Structural engineerusual
Permissions and noticesPlanning / permitted development check, building control application, party-wall notices where applicableApplication fees and party-wall surveyor where applicable - by quotationParty-wall surveyoroptional
Site set-up and protectionSite set-up: welfare, protection, skip and scaffold licences where the highway is usedby someone else's figureSkip hire, Scaffoldingusual
Demolition / strip-outRemove rear wall opening / existing structurescalculated by its recipe-usual
Groundworks and drainageDrainage diversion / new connectionscalculated by its recipe-usual
FoundationsStrip foundations to the engineer's depthcalculated by its recipe-usual
Groundworks and drainageGround-floor slab with insulationcalculated by its recipe-usual
Walls and openingsCavity walls in facing brick and blockcalculated by its recipe-usual
Structural workSteel beam over the opening to the existing houseSteelwork supply, fabrication and crane/lift - by quotationSteel fabricationusual
RoofingPitched roof (or flat roof: swap the recipe)calculated by its recipe-usual
Windows and external doorsWindows and bi-fold / french doorsWindows and doors supply and fit - by quotationWindows and doors supply and fitusual
First fix (carpentry, plumbing, electrics)Electrical first fixcalculated by its recipe-usual
First fix (carpentry, plumbing, electrics)Heating extensioncalculated by its recipe-usual
Plastering and finishingBoard and skim walls and ceilingcalculated by its recipe-usual
FlooringFloor finishcalculated by its recipe-usual
DecoratingDecoratecalculated by its recipe-usual
DecoratingWoodworkcalculated by its recipe-usual
External worksPatio / pathscalculated by its recipe-optional
Commissioning and inspectionsBuilding control completion certificate, electrical and gas certificatesCertificates and inspection fees-usual
Snagging and handoverSnagging and handoverby someone else's figure-usual

What you get

  • Every stage's quantities and hours from its recipe, priced at your rates and prices; the specialist stages as named unknowns until a quotation or your figure resolves them - never a guess
  • Supplier enquiries drafted from the job's facts for scaffold, skips, steel, windows, the professions - approved by you before anything is sent, replies compared like for like
  • Travel, parking and road charges from the dated catalogue; the site questions (welfare, power, water, access, protection, waste) as lines, enquiries and sentences in the document
  • A phased, branded quotation itemised by stage that reconciles to the penny, with provisional allowances shown apart, accepted on a secure link; variations recorded against it