Groundworks and drainage calculator - free

Excavate and concrete strip foundations: calculator for UK builders

Answer the measurements this calculation needs and JobBosh works out the materials with wastage and pack rounding, the labour hours by role, the plant, the waste and the site needs - then prices them from your own figures, a supplier's quotation or a dated price you record. Free, no account needed to start.

What it works out

  • Material: Ready-mix concrete GEN1/GEN3 (foundation grade to spec)
  • Plant: Mini-digger hire (1.5 t) incl. delivery/collection
  • Labour: Excavate trenches (machine + banksman); Place and level concrete
  • Waste: Excavated spoil to remove (grab lorry)

The questions it asks

QuestionUnit / choicesRequired?Help
Trench lengthmrequired
Trench widthmoptional - default 0.6 (labelled assumed)
Trench depthmoptional - default 1.0 (labelled assumed)To the engineer's / building control depth; 1.0 m is common, clay and trees go deeper.
Concrete depthmoptional - default 0.6 (labelled assumed)
Spoil disposalone of: grab lorry, skips, keep on siteoptional - default grab_lorry (labelled assumed)
Can a mini-digger reach the trench?yes / nooptional - default yes (labelled assumed)

The norms behind it, with their sources

Coverage, productivity and wastage defaults you can edit; each carries where it comes from and is shown as assumed until your own benchmark replaces it.

NormValueSourceTier
Excavated soil bulks by ~30 %1.3 xtrade practice (clay 30-40 %)assumed
Mini-digger excavation per m3 incl. driver0.5 hr/m3trade practiceassumed
Hand dig per m33 hr/m3trade practiceassumed
Place and level concrete per m3 (ready-mix, barrowed)0.8 hr/m3trade practiceassumed

A worked example

Answers used: Trench length 4 m; Trench width 0.6 m; Trench depth 1.0 m; Concrete depth 0.6 m; Spoil disposal grab lorry; Can a mini-digger reach the trench? yes. These are the recipe's own quantities for those answers - the prices are yours, the supplier's or a quotation's, never a figure typed on a web page.

KindLineQuantityHow it is worked out
materialReady-mix concrete GEN1/GEN3 (foundation grade to spec)1.51 m3
7 x m3 - delivered in 0.25 m3 steps
4 x 0.6 x 0.6 m +5 %
plantMini-digger hire (1.5 t) incl. delivery/collection1 hire-day2.40 m3 x 0.5 h/m3 / 8 h days
labourExcavate trenches (machine + banksman)2.4 hr2.40 m3 x 0.5 h/m3 x 2 people
labourPlace and level concrete1.15 hr1.44 m3 x 0.8 h/m3
wasteExcavated spoil to remove (grab lorry)3.12 m32.40 m3 x 1.3 bulking

Labour on this example: about 3.55 hours across the roles; at your rates it becomes money.

Site questions this work raises: Site access and neighbours, Parking and traffic, Utilities and welfare, Waste, Commercial and contract.

Specialists or hire it may need, drafted as enquiries from the job's facts: Grab lorry / muck-away, Ready-mix concrete.

Building control inspects the trench before the pour: programme the inspection.

Deeper trenches (over 1.2 m) need support: the engineer's call.

Then what

Price the lines from your crew rates and your material prices (each with its source and date), answer the site questions (parking, skip, welfare, power, water, protection), let JobBosh draft the supplier enquiries you approve, and issue a branded quotation your customer accepts on a secure link. Guest work is kept for 14 days; a free account keeps it for good.